California’s New Groundwater Law: An Interactive Timeline

Hi  Folks —

This information comes from the Legal Planet website.  They put up an interactive timeline, which I have translated into a table.

CA Groundwater Law Timeline

Jane

legal-planet.org
California’s New Groundwater Law: An Interactive Timeline

What are the major deadlines for local groundwater management agencies, and when can-or must-state agencies act?

Posted on October 8, 2014 12:17 pm by Nell Green Nylen

Many (including Legal Planet’s own http://legal-planet.org/2014/09/13/groundwater-management-lite-for-california/Rick Frank) have examined the pros and cons of California’s new locally-focused groundwater management law.  Such analyses will continue to be critically important as state and local players move forward with the nitty-gritty of actual implementation, and the legislation’s practical, on-the-ground (and under-the-ground) implications become clearer.

In this post, however, my goal is to simply lay out the relationships between the many dates and deadlines embedded in the law.  Together, http://leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=201320140SB1168 Senate Bill 1168, http://leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=201320140AB1739&search_keywords= Assembly Bill 1739, and http://leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=201320140SB1319&search_keywords= Senate Bill 1319 impose mandates for sustainable groundwater management on local agencies in high- and medium-priority groundwater basins.  While the legislation puts most of the burden-and the power-in the hands of locals, it also establishes roles for two state agencies: the Department of Water Resources (<http://water.ca.gov/>DWR) and the State Water Resources Control Board (<http://www.swrcb.ca.gov/>SWRCB).

The timeline shows three categories of dates and deadlines displayed in separate, stacked bands: (1) the upper band shows the major deadlines by which DWR must act; (2) the middle band shows the major deadlines that apply to local agencies; and (3) the lower band shows the dates after which SWRCB could potentially intervene to address local management deficiencies.

A brief summary of each of the three categories of dates and deadlines follows.

1.  Major Deadlines for Action by the Department of Water Resources (DWR)

The new groundwater law relies on DWR to jumpstart local groundwater management efforts by laying ground rules and providing information.  First DWR will set the stage by identifying which groundwater basins have to be managed.  By January 31, 2015, it will establish the initial http://www.water.ca.gov/groundwater/casgem/unmonitored.cfm priority-high, medium, low, or very low-for each groundwater basin in the state.  Only high- and medium-priority basins will be subject to sustainable groundwater management mandates.  If DWR later elevates a low- or very-low-priority basin to
“medium” or “high” priority, that basin will have to establish a groundwater sustainability agency within two years and adopt a groundwater sustainability plan within five. (Water Code § 10722.4).  Although http://water.ca.gov/groundwater/casgem/basin_prioritization.cfm DWR already prioritizes groundwater basins, the legislation adds a new consideration (“adverse impacts on local habitat and local streamflow”) for DWR to take into account.  (Water Code § 10933(b)(8)).

Next, DWR must develop two sets of emergency regulations to govern how DWR and local groundwater agencies interact.  Since the legislation allows local agencies to request basin-boundary revisions, it tasks DWR with adopting regulations that detail the substance and process of boundary review by January 1, 2016.  (Water Code § 10722.2).  Additionally, by June 1, 2016, DWR must adopt regulations for evaluating groundwater sustainability plans, their implementation, and coordination agreements between local agencies for groundwater sustainability planning.  (Water Code § 10733.2).

By December 31, 2016, DWR must publish its best estimate of how much water is available for groundwater replenishment “in the state.”  By the following day, January 1, 2017, DWR has to publish best management practices for sustainable groundwater management.

These deadlines are all front-loaded, with DWR’s actions occurring before deadlines for local agency action come due, but the legislation imposes other deadlines on DWR that are keyed to specific local agency actions instead of to absolute dates.  For example, DWR must evaluate and issue an assessment of each groundwater sustainability plan within 2 years of the date a local agency submits it, then review plans and plan alternatives (see below) at least every five years.  (Water Code §§ 10733.4(d), 10733.8).

2.  Major Deadlines that Apply to Local Agencies

The deadlines for local agencies’ actions begin on the same date DWR’s date-linked deadlines end.

First, if a local agency intends to use an alternative to a groundwater sustainability plan, it must submit that alternative to DWR by January 1, 2017, as well as every five years thereafter.  (Water Code § 10733.6)

Second, if DWR has not approved an alternative (and one is not pending approval), each high- or medium-priority basin must have identified / formed a groundwater sustainability agency by June 30, 2017.  (Water Code §§ 10724, 10735.2(a)(1)).  Any groundwater extractions that take place in parts of basins that lie outside these agencies’  management areas must be reported directly to SWRCB starting on July 1, 2017.  (Water Code §§ 5202, 10724)

The next group of deadlines marks when high- and medium-priority basins must be managed under groundwater sustainability plans.  Basins designated as having critical conditions of overdraft must be managed under groundwater sustainability plans by January 31, 2020.  (Water Code § 10720.7(a)(1)).  For all remaining high- and medium-priority basins, the deadline comes two years later, on January 31, 2022.  (Water Code § 10720.7(a)(2)).  Subsequently, groundwater sustainability agencies have to submit annual reports to DWR.  The reports must include information about groundwater elevation, (aggregated) groundwater extraction, use and availability of surface water for recharge or in-lieu use, total water use, and the change in groundwater storage.  (Water Code § 10728)

Within twenty years of the date a groundwater sustainability plan is implemented, a basin is supposed to achieve sustainability (operating within the basin’s sustainable yield).  (Water Code § 10727.2(b)).  However, DWR can give up to two five-year extensions on meeting this goal.  (Water Code § 10727.2(b)(3)).

3.  Dates After Which the State Water Resources Control Board (SWRCB) Could Intervene in Local Groundwater Management

In contrast with the hard deadlines it sets for DWR and local-agency action, the legislation identifies a series of dates and other threshold requirements that must be met before SWRCB may-but is not required to-intervene to address deficiencies in local groundwater management.

There are two main stages of intervention possible: probation and interim planning/management.

First, SWRCB can assign probationary status to a basin that has (1) missed a deadline (e.g., to form a groundwater sustainability agency, submit an alternative, or adopt a groundwater sustainability plan), (2) developed an inadequate groundwater sustainability plan, or (3) implemented a plan inadequately.   The legislation includes different dates/thresholds for different types of probation that generally correspond with the passage of a local agency deadline.  For example, the earliest possible date SWRCB can put a basin on probation is June 30, 2017 (e.g., if the basin lacks a groundwater sustainability agency).  However, SWRCB can’t put a basin in which groundwater extractions result in significant depletions of interconnected surface waters on probation for inadequate planning or implementation until January 3 1, 2025, at the earliest. (Water Code § 10735.2).  Beginning ninety days after SWRCB puts a basin on probation, all groundwater extractions must be reported directly to SWRCB.  (Water Code §§ 5202).

The second stage of intervention occurs if SWRCB decides to develop an interim plan for a basin it has placed on probation, often after a substantial waiting period that allows the applicable groundwater sustainability agency time to address the problem. (Water Code §§ 10735.4, 10735.6, 10735.8).

What do these dates and deadlines tell us?

We can draw many inferences from the above dates and deadlines and how they interact with one another.  Most obviously (and as many others have noted), the legislation is not a quick fix for http://waterinthewest.stanford.edu/groundwater/overview/ California’s groundwater woes.  Even if every high- and medium-priority groundwater basin meets every deadline, every groundwater sustainability plan is adequate, and each is implemented appropriately, we would not expect to achieve sustainable groundwater management (basins operating at sustainable yield) for at least a quarter of a century.  Longer if we factor in DWR’s ability to give up to two five-year extensions on that deadline.

Beyond this straightforward look at the timeline for implementing California’s new groundwater law, there are many other levels on which we can analyze the legislation and its impacts.  We plan to do so.